= Current Run Plan =  
 
= Current Run Plan =  
 
* Short-term run plan: https://hallcweb.jlab.org/wiki/index.php/Short_Term_Run-Plan
 
* Short-term run plan: https://hallcweb.jlab.org/wiki/index.php/Short_Term_Run-Plan
** KinC_x36_6  
+
** KinC_x36_6, NPS at 7.5 deg, calorimeter at 6m
** DIS singles scans (NPS calo off), starting around 11am, takes about ~2h
+
** Positron data taking today?
** BCM calibrations, starting around 1pm including the Faraday cup measurements (0.5h), total about ~2h
+
** Moller measurements on Thursday?
  
 
= Notices in Effect for Shift Crew =
 
= Notices in Effect for Shift Crew =

Revision as of 10:04, 27 February 2024

RC Meeting Information

RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)

Useful Links

Hall status


Accelerator status

  • West arc box supplies dropped off at 7am, downtime for ~2.5h
  • Maintenance + Beam study on Wednesday
    • Beam off at 7am
    • Maintenance till around noon
    • Beam study till 21:00pm
    • Beam to the halls, ~22:30pm
    • Scheduled can be shifted a bit if the maintenance work finished earlier

Current Run Plan

Notices in Effect for Shift Crew

Current Issues

  • NPS crate #2 drops occasionally
    • Not much reported recently, taking 30min runs (restarting a new run more often) seems helping
  • BTA with low current - https://logbooks.jlab.org/entry/4256075
    • Helper script: go_bta_config
  • NPS crate temperatures:

Planned Access to the Hall

Special Requests

  • Guard house work till Friday. Pay attention to the sign and follow the directions around there when coming to the accelerator site.