# RHEL9 upgrade preparation is on-going
 
# RHEL9 upgrade preparation is on-going
 
# Checked with Chris Cuevas: SOLID FADC will probably be available by end of November, and he should have enough SD boards for us now.
 
# Checked with Chris Cuevas: SOLID FADC will probably be available by end of November, and he should have enough SD boards for us now.
 +
# LAD will run with 1 uA for production, and (>)5 uA for optics (SHMS+HMS)

Revision as of 15:10, 9 October 2024

Back to Main Page >> Weekly meetings

Agenda

Notes

Updates:

  1. Both HMS and SHMS DAQ are ready to take cosmic runs
  2. HMS cosmic looks good (FADC uses Hall D firmware)
  3. SHMS cosmic TDC and DC look good, but the replay root files don't have FADC events (Hall B firmware), could be the decoder is not set up correctly to decode Hall B firmware
  4. RHEL9 upgrade preparation is on-going
  5. Checked with Chris Cuevas: SOLID FADC will probably be available by end of November, and he should have enough SD boards for us now.
  6. LAD will run with 1 uA for production, and (>)5 uA for optics (SHMS+HMS)