Meeting Information
- Location CC L210A, 11 am
- DocDB
Blue Jeans Connection Information
- https://bluejeans.com/895800575
- Just want to dial in on your phone?
- +1.408.740.7256 (US)
- +1.888.240.2560 (US Toll Free)
- +1.408.317.9253 (Alternate number)
- http://bluejeans.com/numbers
- Enter Meeting ID: 895800575
- Press #
Agenda
- Commissioning plan updates from detector systems
- Status update from detector owners, calibrations, efficiencies, etc.
- Review systems owners and update information
- Address system specific points of interest for the Fall 2017 run
Minutes
General
- We briefly discussed the Fall 2017 Commissioning Plan
- The summary table needs to be updated and tasks need to be assigned
- We discussed the shift schedule
- Shift crew will need to refer to a good wiki page
- Dave G. Noted that ALL shift crew need to have the Hall walk through prior to locking up so that they can sit shift
- We discussed the shift schedule
- The official version and sign up period will go out in about a week or so
- We need to ensure that we have the necessary RSAD and OSP documents readily available on the wiki
- We need and OSP for the GEM and drift chambers
HMS
12 GeV Drift Chambers
- Carlos showed a few log entries regarding the chamber work on the HMS platform
- Chamber signals
- Individual wire signals were investigated with a wire terminator and they look great
- The logic pulse produced by the discriminator cards looks extremely stable
- Wire maps were shown with cosmic data taken overnight
- There are utilizing scintillator triggers with two on the top and two on the bottom
- After fixing a connectivity issue the updated maps look good
- Some efficiency plots were shown
- They look rather good
- 99% efficiency is expected in the range of 1900 - 2200 V which is currently being observed
- The planes appear to plateau at 1940V at a threshold of 4.5 V
Hodoscopes
- Simona will checkout the PMTs this afternoon
- Only 3 planes will be checked out since 5 paddles from the first plane are being utilized for the 12 GeV chamber tests
Heavy Gas Cherenkov
- C4F8O OR C4F10O will be in the tank
- It is unclear at the moment which pressure will be utilized
- This needs to be followed up on
Shower
- Arshak reported that they plan to take cosmic data soon
SHMS
GEM
- Steve reported that the timing is now understood
- The TI latency was being set to be extremely large
- This was reduced and behaved in an expected way
- The dynamic range in the timing now looks to be okay
- The TI delay was reduced overall by approximately 0.5 us
- The new optical fiber in SHMS hut is now being utilized instead of the previous HMS patch
- Latif reported that overnight cosmic data has been taken
- Pedestal correction and map work is ongoing
- Work is ongoing to investigate the possibility of noise and zero suppression, Steve is looking into this
- Latif is looking into how exactly to set the thresholds relative to the baseline
Noble Gas Cherenkov
- Out for commissioning
- Will be there for F2
Hodoscopes
- Simona reported on the quartz plane
- She can make 4 per day
- 11 are curing currently and should be done by Saturday and then flipped and should be done by the following Saturday
- All bars should be done around Nov 5
- When the frame comes down S2X will come with it
Aerogel Cerenkov
- Vlad reported they have a new HV module and it will be installed later this afternoon
- The previous HV module has been causing problems
- One PMT is questionable, but a spare is on the way
- They are looking at data and it looks reasonable
- This tube has been carefully investigated although they are almost certain it is the tube itself
Shower/Pre-shower
- They have been taking cosmic data and all channels are alive but will be looked at further