Difference between revisions of "Fall 2017 Commissioning Plan"
From HallCWiki
Jump to navigationJump to searchLine 10: | Line 10: | ||
|- | |- | ||
| HMS & SHMS hodoscope checkout | | HMS & SHMS hodoscope checkout | ||
− | | | + | | S. Malace |
| | | | ||
|- | |- | ||
Line 17: | Line 17: | ||
| | | | ||
|- | |- | ||
− | | HMS & SHMS DC checkout, | + | | HMS & SHMS DC checkout, tracking efficiency and alignment |
− | | | + | | H. Szumila-Vance, C. Yero |
+ | | | ||
+ | |- | ||
+ | | HMS & SHMS heavy gas Cherenkov checkout | ||
+ | | E. Pooser, R. Ambrose | ||
+ | | | ||
+ | |- | ||
+ | | HMS & SHMS pre-shower/shower checkout | ||
+ | | H. Mkrtchyan, A. Asaturyan, V. Berdnikov | ||
| | | | ||
|- | |- | ||
− | | | + | | SHMS aerogel checkout |
− | | | + | | H. Mkrtchyan, A. Asaturyan, V. Berdnikov |
| | | | ||
|- | |- | ||
| HMS & SHMS 3/4 trigger efficiency checkout | | HMS & SHMS 3/4 trigger efficiency checkout | ||
− | | | + | | B. Sawatzky, E. Pooser, C. Yero |
| | | | ||
|- | |- | ||
| HMS & SHMS PID trigger efficiency checkout | | HMS & SHMS PID trigger efficiency checkout | ||
− | | | + | | B. Sawatzky, E. Pooser, C. Yero |
| | | | ||
|- | |- |
Revision as of 15:11, 11 October 2017
Table of Commissioning Tasks
Task | Person | Comment |
Harp scans, BPM and raster checkout | M. Jones | |
HMS & SHMS hodoscope checkout | S. Malace | |
SHMS quartz plane | S. Malace | |
HMS & SHMS DC checkout, tracking efficiency and alignment | H. Szumila-Vance, C. Yero | |
HMS & SHMS heavy gas Cherenkov checkout | E. Pooser, R. Ambrose | |
HMS & SHMS pre-shower/shower checkout | H. Mkrtchyan, A. Asaturyan, V. Berdnikov | |
SHMS aerogel checkout | H. Mkrtchyan, A. Asaturyan, V. Berdnikov | |
HMS & SHMS 3/4 trigger efficiency checkout | B. Sawatzky, E. Pooser, C. Yero | |
HMS & SHMS PID trigger efficiency checkout | B. Sawatzky, E. Pooser, C. Yero | |
Beam energy | M. Jones, D. Mack | |
BCM Calibration | D. Mack, D. Bhetuwal | |
Target Boiling | D. Gaskell | |
Carbon elastic with sieve for final SHMS tune determination | M. Jones, H. Szumila-Vance | |
Carbon elastic scan for delta matrix optimization | H. Bhatt, D. Dutta | |
Carbon inelastics with sieve for Ytgt, Y’tgt and X’tgt ( Need 20 deg for Ytgt) | M. Jones, H. Szumila-Vance | |
Sieve check after cycling SHMS magnets from positive to negative and back | M. Jones | |
Determine SHMS central momentum and angle with set of elastic ep data. | A. Karki, S. Basnet, D. Dutta | |
Inelastic carbon xn measurements with overlapping momentum settings to for acceptance check. | M. Jones, B. Duran | |
GEM front sieve to better understand HB. Do optics with p+ to check optics. | L. Kabir, D. Dutta | |
Coincidence timing checkout and optimization. | B. Sawatzky, E. Pooser, C. Yero | |
Electronic dead time checkout | B. Sawatzky, E. Pooser, C. Yero | |
Single Kaon production. Coincidence p and K production. |
Fall 2017 Commissioning Plan
- The plan will be base on the plan of the full SHMS/HMS commissioning.