Difference between revisions of "Fall 2017 Commissioning Plan"
From HallCWiki
Jump to navigationJump to searchLine 13: | Line 13: | ||
| | | | ||
|- | |- | ||
− | | SHMS Quartz Plane | + | | HMS & SHMS 3/4 Trigger & TOF Efficiency Checkout |
+ | | S. Malace | ||
+ | | | ||
+ | |- | ||
+ | | SHMS Quartz Plane Checkout | ||
| S. Malace | | S. Malace | ||
| | | | ||
Line 33: | Line 37: | ||
| | | | ||
|- | |- | ||
− | | HMS & SHMS | + | | HMS & SHMS Trigger Efficiency Checkout |
− | |||
− | |||
− | |||
− | |||
| B. Sawatzky, E. Pooser, C. Yero | | B. Sawatzky, E. Pooser, C. Yero | ||
| | | |
Revision as of 06:31, 12 October 2017
Table of Commissioning Tasks
Task | Person | Comment |
Harp Scans, BPM and Raster Checkout | M. Jones | |
HMS & SHMS Hodoscope Checkout | S. Malace | |
HMS & SHMS 3/4 Trigger & TOF Efficiency Checkout | S. Malace | |
SHMS Quartz Plane Checkout | S. Malace | |
HMS & SHMS DC Checkout, Tracking Efficiency and Alignment | H. Szumila-Vance, C. Yero | |
HMS & SHMS Heavy Gas Cherenkov Checkout | E. Pooser, R. Ambrose | |
HMS & SHMS Pre-Shower/Shower Checkout | H. Mkrtchyan, A. Asaturyan, V. Berdnikov | |
SHMS Aerogel Checkout | H. Mkrtchyan, A. Asaturyan, V. Berdnikov | |
HMS & SHMS Trigger Efficiency Checkout | B. Sawatzky, E. Pooser, C. Yero | |
Beam Energy | M. Jones, D. Mack | |
BCM Calibration | D. Mack, D. Bhetuwal | |
Target Boiling | D. Gaskell | |
Carbon Elastic with Sieve for Final SHMS Tune Determination | M. Jones, H. Szumila-Vance | |
Carbon Elastic Scan for Delta Matrix Optimization | H. Bhatt, D. Dutta | |
Carbon Inelastics with Sieve for Ytgt, Y’tgt and X’tgt (Need 20 deg for Ytgt) | M. Jones, H. Szumila-Vance | |
Sieve Check After Cycling SHMS Magnets from Positive to Negative and Back | M. Jones | |
Determine SHMS Central Momentum and Angle with Set of Elastic ep Data | A. Karki, S. Basnet, D. Dutta | |
Inelastic Carbon Xn Measurements with Overlapping Momentum Settings for Acceptance Check | M. Jones, B. Duran | |
GEM Front Sieve to Better Understand HB. Do Optics with p+ to Check Optics | L. Kabir, D. Dutta | |
Coincidence Timing Checkout and Optimization | B. Sawatzky, E. Pooser, C. Yero | |
Electronic Dead Time Checkout | B. Sawatzky, E. Pooser, C. Yero | |
Single Kaon Production. Coincidence p and K Production |
Fall 2017 Commissioning Plan
- The plan will be base on the plan of the full SHMS/HMS commissioning.