Line 21: Line 21:
 
|Q2=4.4 W=2.74 x=0.4 theta_Shms=15.81 || Completed || 68 % of stat goal on LH2; Al done [https://logbooks.jlab.org/entry/3606081 Summary plot of SHMS Center and Left]
 
|Q2=4.4 W=2.74 x=0.4 theta_Shms=15.81 || Completed || 68 % of stat goal on LH2; Al done [https://logbooks.jlab.org/entry/3606081 Summary plot of SHMS Center and Left]
 
|-
 
|-
|Q2=3. W=3.14 x=0.25 theta_Shms=12.42 || LH2 in progress || got 12% of stat goal so far on LH2
+
|Q2=3. W=3.14 x=0.25 theta_Shms=12.42 || LH2 in progress || got 36% of stat goal so far on LH2
 
|-
 
|-
 
|Q2=3. W=3.14 x=0.25 theta_Shms=9.42 || To do ||  
 
|Q2=3. W=3.14 x=0.25 theta_Shms=9.42 || To do ||  

Revision as of 22:25, 8 October 2018

  • Table of Kaon LT Physics Status at Ebeam = 10.6 GeV
Item Status Comment
Q2=3.0 W=2.32 x=0.40 theta_Shms=15.18 Completed
Q2=3.0 W=2.32 x=0.40 theta_Shms=18.18 Completed
Q2=3.0 W=2.32 x=0.40 theta_Shms=21.18 Completed Summary plot of all three settings, updated Oct 6
Q2=2.115 W=2.95 x=0.21 theta_Shms=7.74 Completed ~43 % of stat goal on LH2; Al done [1]
Q2=2.115 W=2.95 x=0.21 theta_Shms=10.74 Completed 43 % of stat goal on LH2; Al done [2]
Q2=2.115 W=2.95 x=0.21 theta_Shms=13.74 Completed 43 % of stat goal on LH2; Al done [3] Summary plot of all three settings
Q2=4.4 W=2.74 x=0.4 theta_Shms=9.81 Completed 58% of stat goal on LH2; Al done Summary plot of SHMS Right
Q2=4.4 W=2.74 x=0.4 theta_Shms=12.81 Completed 62% of the stat goal on LH2; Al done
Q2=4.4 W=2.74 x=0.4 theta_Shms=15.81 Completed 68 % of stat goal on LH2; Al done Summary plot of SHMS Center and Left
Q2=3. W=3.14 x=0.25 theta_Shms=12.42 LH2 in progress got 36% of stat goal so far on LH2
Q2=3. W=3.14 x=0.25 theta_Shms=9.42 To do
Q2=3. W=3.14 x=0.25 theta_Shms=6.65 To do
Q2=5.5 W=3.02 x=0.4 theta_Shms=6.65 To do
Q2=5.5 W=3.02 x=0.4 theta_Shms=9.56 To do
Q2=5.5 W=3.02 x=0.4 theta_Shms=12.56 To do
  • Table of Kaon LT Commissioning Status.
Item Status Comment
Detector Checkout Completed
HMS Trigger PID Completed
SHMS Trigger PID Completed
BPM calibration check Not done
Beam energy measurement Completed [4]
High and low current BCM calibration Completed low current up to 57uA Calibration plots
HMS/SHMS optics study Completed
HMS/SHMS single arm elastic Completed
HMS/SHMS coincidence ep elastic Completed 25K events ( wanted 50K)
Golden HMS/SHMS sieve run Completed Used to check the stability of beam positions at different energies
Luminosity scan Not done Need fairly stable 65uA