Commissioning

Beam checkout

Detailed beam checkout instructions can be found here.

HMS SHMS TARGET RADIATOR I (uA) RASTER DURATION Q (C) TRIGGER DAQ STATUS
P P
Harp Scan Empty out 5 OFF 0:15 done
YAG: Beam spot Empty out tune OFF 0:05 done
YAG: Raster check Empty out tune 2x2 0:10 done
Carbon hole 4.712 17.08 (-) 5.389 15.81 (-) C-hole out 5 3x3 0:30 3/4 sep. done

Detector checkout and calibrations

Additional instructions:

  • We run both the COIN and separate DAQs during this phase!
  • Inelastic measurement:
    • Take 5min of MODE 10 data before starting the the inelastic measurement, then switch back to MODE 9.
  • Coinc elastic:
    • Take 5min of MODE 10 data before starting the the inelastic measurement, then switch back to MODE 9.
    • Take pre-scaled 3/4 singles in both arms, set pre-scalers so the singles rate is <100Hz
    • This run needs a special temporary trigger that will be connected to PS5
    • Make sure sure PS5 = 0
HMS SHMS TARGET RADIATOR I (uA) RASTER DURATION Q (C) TRIGGER DAQ STATUS
P THETA P THETA
Trigger checkout 4.712 17.08 (-) 5.389 15.81 (-) LH2 out 70 2x2 0:15 3/4 COIN done
PID checkout 4.712 17.08 (-) 5.389 15.81 (-) LH2 out 70 2x2 0:15 3/4 COIN done
PID checkout 3.5 21 (-) 3.5 21 (-) LH2 out 70 2x2 0:15 3/4 COIN skip
ECAL calibration 4.75 21 (-) 4.75 21 (-) LH2 out 70 2x2 0:15 3/4 COIN done
inelastic/ECAL calib 4.1 21 (-) 3.5 25 (-) LH2 out 70 2x2 ELREAL sep. done
inelastic 4.1 21 (-) 3.5 25 (-) Dummy out 40 2x2 ELREAL sep. done
optics (SIEVE) 4.1 21 (-) 3.5 25 (-) Optics-1 out 65 2x2 ELREAL sep. done

Unscheduled single-arm Run Plan

COMPLETED

Replaces original radiator and production trigger checkout. Click here for the single-arm SHMS run plan

Coincidence calibration

  • For mode 10 run: put HMS 3/4 + SHMS ELCLEAN into ps5, set DAQ to MODE10
  • For next runs: revert DAQ to MODE 9, keep trigger the same
  • When done with this measurements, revert ps5 to be HMS ELCLEAN + SHMS 3/4
HMS SHMS TARGET RADIATOR I (uA) RASTER DURATION Q (C) TRIGGER DAQ
P THETA P THETA
Mode 10 4.618 27.18 (+) 6.826 18 (-) LH2 out 70 2x2 0:05 ps5 (rev.) COIN
coinc elastic 4.618 27.18 (+) 6.826 18 (-) LH2 out 70 2x2 0:30 0.13 ps5 (rev.) COIN
coinc elastic 4.618 27.18 (+) 6.826 18 (-) Dummy out 40 2x2 0:10 0.02 ps5 (rev.) COIN
TIME (days) 0.03
Charge(mC) 150

Production

Production phase 1 (Production checkout and 66% of High-E/low-t point)

Additional instructions:

  • High-E/low-t:
    • Take 5min of MODE 10 data before starting each polarity, then switch back to MODE 9.
    • Make sure to do at least one dummy run every shift
    • Make sure to do at least one 30min radiator-out run every shift
    • Make sure the production pre-scaler is set to 0
    • Take pre-scaled 3/4 singles in both arms, set pre-scalers so the singles rate is <100Hz
HMS SHMS Target Radiator I (uA) Raster Duration Q (C) Trigger DAQ
P THETA P THETA
High E/low t 4.95 19.1 (+) 4.835 17 (-) LH2 in 70 2x2 8:00 2.02 production COIN
High E/low t 4.95 19.1 (+) 4.835 17 (-) Dummy in 40 2x2 2:45 0.40 production COIN
High E/low t 4.95 19.1 (+) 4.835 17 (-) LH2 out 70 2x2 1:20 0.34 production COIN
test: Mid E/ low t 4.6 19.9 (+) 4.3 20.1 (-) LH2 in 70 2x2 0:30 0.13 3/4 (HMS) + 3/4 (SHMS) COIN
test: high t 4.08 16.4 (+) 3.5 30 (-) LH2 in 70 2x2 0:30 0.13 3/4 (HMS) + 3/4 (SHMS) COIN
optics HMS 4.95 21.768 (-) 4.835 17 (+) Optics out 65 2x2 0:30 0.12 ELREAL HMS HMS
High E/low t 4.95 19.1 (-) 4.835 17 (+) LH2 in 70 2x2 8:00 2.02 production COIN
High E/low t 4.95 19.1 (-) 4.835 17 (+) Dummy in 40 2x2 2:45 0.40 production COIN
High E/low t 4.95 19.1 (-) 4.835 17 (+) LH2 out 70 2x2 1:20 0.34 production COIN

Production phase 2 (66% of Mid-E/low-t point)

Additional instructions:

  • Mid-E/low-t:
    • Take 5min of MODE 10 data before starting each polarity, then switch back to MODE 9.
    • Make sure to do at least one dummy run every shift
    • Make sure to do at least one 30min radiator-out run every shift
    • Make sure the production pre-scaler is set to 0
    • Take pre-scaled 3/4 singles in both arms, set pre-scalers so the singles rate is <100Hz
HMS SHMS Target Radiator I (uA) Raster Duration Q (C) Trigger DAQ
P THETA P THETA
Mid E/low t 4.6 19.9 (-) 4.3 20.1 (+) LH2 in 70 2x2 16:00 4.03 production COIN
Mid E/low t 4.6 19.9 (-) 4.3 20.1 (+) Dummy in 40 2x2 5:30 0.79 production COIN
Mid E/low t 4.6 19.9 (-) 4.3 20.1 (+) LH2 out 70 2x2 2:40 0.67 production COIN
test: high t 4.08 16.4 (-) 3.5 30 (+) LH2 in 70 2x2 0:30 0.13 3/4 (HMS) + 3/4 (SHMS) COIN
Mid E/low t 4.6 19.9 (+) 4.3 20.1 (-) LH2 in 70 2x2 16:00 4.03 production COIN
Mid E/low t 4.6 19.9 (+) 4.3 20.1 (-) Dummy in 40 2x2 5:30 0.79 production COIN
Mid E/low t 4.6 19.9 (+) 4.3 20.1 (-) LH2 out 70 2x2 2:40 0.67 production COIN

Production phase 3 (50% of high-t point)

Additional instructions:

  • high-t:
    • Take 5min of MODE 10 data before starting each polarity, then switch back to MODE 9.
    • Make sure to do at least one dummy run every shift
    • Make sure to do at least one 30min radiator-out run every shift
    • Make sure the production pre-scaler is set to 0
    • Take pre-scaled 3/4 singles in both arms, set pre-scalers so the singles rate is <100Hz
HMS SHMS Target Radiator I (uA) Raster Duration Q (C) Trigger DAQ
P THETA P THETA
high t 4.08 16.4 (+) 3.5 30 (-) LH2 in 70 2x2 48:00 12.10 production COIN
high t 4.08 16.4 (+) 3.5 30 (-) Dummy in 40 2x2 16:30 2.38 production COIN
high t 4.08 16.4 (+) 3.5 30 (-) LH2 out 70 2x2 8:00 2.02 production COIN
high t 4.08 16.4 (-) 3.5 30 (+) LH2 in 70 2x2 48:00 12.10 production COIN
high t 4.08 16.4 (-) 3.5 30 (+) Dummy in 40 2x2 16:30 2.38 production COIN
high t 4.08 16.4 (-) 3.5 30 (+) LH2 out 70 2x2 8:00 2.02 production COIN

Production phase 4

TBD based on results from first production phases and beam quality.