Sep 20, 2022

From HallCWiki
Jump to navigationJump to search

RC Meeting Information

RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)

  • Zoom remote connection information:
 Join ZoomGov Meeting
 https://jlab-org.zoomgov.com/j/1607100885?pwd=ZFBsRTFsYm5Zb0laZ0tyZXNjcEE0QT09
 Meeting ID: 160 710 0885
 Passcode: 595071
 One tap mobile
 +16692545252,,1607100885# US (San Jose)
 +16468287666,,1607100885# US (New York)
 Dial by your location
       +1 669 254 5252 US (San Jose)
       +1 646 828 7666 US (New York)
       +1 669 216 1590 US (San Jose)
       +1 551 285 1373 US
       833 568 8864 US Toll-free
 Meeting ID: 160 710 0885
 Find your local number: https://jlab-org.zoomgov.com/u/ab2CekLXgQ

Useful Links

Current Status

Current Run Plan

  • Resume beam tune to Hall C / Ion Chamber calibration with "No target" ( DONE )
  • Do "Aluminum Hole" check to center BEAM on target ( DONE )
  • Do Ion Chamber calibration for solid (using Thorium, 6% R.L.), and cryotargets (LH2, LD2) ( DONE )
  • Ramp back up SHMS magnets to do trigger checkout using LH2 ( DONE )
  • Do SHMS Hodo HV test / proton absorption / heep normalization ( DONE )
  • Proceed to CaFe production @ mean-field kinematics for all targets ( IN-PROGRESS )
    • LD2 - DONE
    • Al Dummy - DONE
    • C12 - DONE
    • Ca48 - DONE
    • Ca40 - DONE
    • Fe54 - DONE
    • Be9 - DONE
    • B10 - DONE
    • B11 - DONE
  • Proceed to CaFe production @ src kinematics for all targets ( IN-PROGRESS )
    • Ca40 - IN-PROGRESS
    • Ca48 - PENDING
    • Fe54 - PENDING
    • C12 - PENDING
    • LD2 - PENDING
    • Be9 - PENDING
    • B10 - PENDING
    • B11 - PENDING
    • Al Dummy - PENDING


  • Whenever MCC is able to deliver 70-75 uA stable beam current:
    • coordinate with D. Mack to do BCM calibrations ( PENDING )
    • do Target Boiling study whenever we have LD2 target in place (to save time of having to do target changes) ( PENDING )

Notices in Effect for Shift Crew

Current Issues

Planned Accesses to the Hall

Planned Accelerator Configuration Changes

Special Requests

  • During RF recovery tomorrow, we would like to schedule a Hall C Walkthrough for some users, but a time frame of when RF recovery will be done is needed. Shawn Frierson has been contacted. Awaiting response . . .