Minutes Hall C Meeting 3/4/2013

  • Walter Kellner
    • The SOS base frame was removed from the Hall.
    • Last bit of SOS rail was removed
    • The C-can and platform have been dismounted
    • The Hall C crane is still down for repairs. Expected to be back in service this week. In the mean time a crane is being rented from Lockwood
    • The groundwater leak in the truck ramp has finally been fixed
    • There is still a bad leak near the labyrinth door
  • Mike Fowler
    • The SHMS rail installation is complete
    • The SHMS structure assembly is being sent out for rebidding. This will delay the SHMS structure assembly by a month.
  • Joe Beaufait (via email)
    • Spoke to engineering group for help with rerouting of G0 patch panel
    • G0 water cooled leads found. Are in good enough condition to reuse.
    • Clean power water issue reported as resolved by facilities, but Joe has not been able to get a report on what was actually done.
  • Paul Brindza
  • Bert Manzlak
    • Reminds people to check with Walter or Andy before coming into hall