RC Meeting, Thursday, August 23
From HallCWiki
Jump to navigationJump to search
- General
- Beamline vacuum still not great
- Beam likely not ready to send to hall until Friday
- LN2 vendor has supply issues - JLab usually gets 2 trucks/day - vendor can only provide 1 truck/day. Alternate supplies under investigation.
- Target
- Target warmed up due to LN2 issue
- Target cooldown??
- SHMS
- After beampipe adjusted, SHMS rotated to 5.69 degrees, but SHMS touched beampipe
- Minimum safe angle will be 6 degrees
- Remote motion control allowed down to 7 degrees - for angles below 7 degrees, all motion will be disabled once set (this includes HMS!). Any rotation after will require access
- HMS
- After beampipe adjusted, and some modification to cable conduit, able to rotate to about 10.9 degrees. Minimum angle will be 11 degrees. Remote motion allowed down to 12.75 degrees
- Minimum separation between SHMS and HMS 21.5 degrees
- DAQ