Run plan for J/psi-007
From HallCWiki
Main | Online | RC | Run Plan | Official Website | Redmine | Index | Nav
Commissioning
Beam checkout
Detailed beam checkout instructions can be found here.
HMS | SHMS | TARGET | RADIATOR | I (uA) | RASTER | DURATION | Q (C) | TRIGGER | DAQ | STATUS | |||||
P | P | ||||||||||||||
Harp Scan | Empty | out | 5 | OFF | 0:15 | done | |||||||||
YAG: Beam spot | Empty | out | tune | OFF | 0:05 | done | |||||||||
YAG: Raster check | Empty | out | tune | 2x2 | 0:10 | done | |||||||||
Carbon hole | 4.712 | 17.08 | (-) | 5.389 | 15.81 | (-) | C-hole | out | 5 | 3x3 | 0:30 | 3/4 | sep. | done |
Detector checkout and calibrations
Additional instructions:
- We run both the COIN and separate DAQs during this phase!
- Inelastic measurement:
- Take 5min of MODE 10 data before starting the the inelastic measurement, then switch back to MODE 9.
- Coinc elastic:
- Take 5min of MODE 10 data before starting the the inelastic measurement, then switch back to MODE 9.
- Take pre-scaled 3/4 singles in both arms, set pre-scalers so the singles rate is <100Hz
- This run needs a special temporary trigger that will be connected to PS5
- Make sure sure PS5 = 0
HMS | SHMS | TARGET | RADIATOR | I (uA) | RASTER | DURATION | Q (C) | TRIGGER | DAQ | STATUS | |||||
P | THETA | P | THETA | ||||||||||||
Trigger checkout | 4.712 | 17.08 | (-) | 5.389 | 15.81 | (-) | LH2 | out | 70 | 2x2 | 0:15 | 3/4 | COIN | done | |
PID checkout | 4.712 | 17.08 | (-) | 5.389 | 15.81 | (-) | LH2 | out | 70 | 2x2 | 0:15 | 3/4 | COIN | done | |
PID checkout | 3.5 | 21 | (-) | 3.5 | 21 | (-) | LH2 | out | 70 | 2x2 | 0:15 | 3/4 | COIN | skip | |
ECAL calibration | 4.75 | 21 | (-) | 4.75 | 21 | (-) | LH2 | out | 70 | 2x2 | 0:15 | 3/4 | COIN | done | |
inelastic/ECAL calib | 4.1 | 21 | (-) | 3.5 | 25 | (-) | LH2 | out | 70 | 2x2 | ELREAL | sep. | done | ||
inelastic | 4.1 | 21 | (-) | 3.5 | 25 | (-) | Dummy | out | 40 | 2x2 | ELREAL | sep. | done | ||
optics (SIEVE) | 4.1 | 21 | (-) | 3.5 | 25 | (-) | Optics-1 | out | 65 | 2x2 | ELREAL | sep. | done |
Unscheduled single-arm Run Plan
COMPLETED
Replaces original radiator and production trigger checkout. Click here for the single-arm SHMS run plan
Coincidence elastics
- * Trigger:
- run with ps6=0
- Remember to click "save" when changing the pre-scalers!
- J/psi-007 Instructions for Shift Takers
- Do a 50k replay for every run. Carefully check the monitoring plots and discuss anything that looks strange with the analysis shift crew.
- Fill out the Shift check list once every shift
HMS | SHMS | TARGET | RADIATOR | I (uA) | RASTER | DURATION | Q (C) | TRIGGER | DAQ | STATUS | |||||
P | THETA | P | THETA | ||||||||||||
coinc elastic | 4.95 | 25.6 | (+) | 6.5 | 19.2 | (-) | LH2 | out | 70 | 2x2 | 0:40 | 0.17 | 3/4 coin | COIN | done |
coinc elastic | 4.95 | 25.6 | (+) | 6.5 | 19.2 | (-) | Dummy | out | 40 | 2x2 | 0:15 | 0.04 | 3/4 coin | COIN | done |
TIME (days) | 0.04 | ||||||||||||||
Charge(mC) | 204 |
Production
Phase 1: high-E/low-t
Instructions:
- Trigger:
- ps6=0 is production trigger
- alse enable ps1 and ps4, pre-scaled to <100Hz
- Remember to click "save" when changing the pre-scalers!
- MODE 10 runs:
- Set DAQ to MODE 10 and click "save" in the pre-scaler GUI
- Remember to go back to MODE 9 when done (and click "save" again!)
- J/psi-007 Instructions for Shift Takers
- Do a 50k replay for every run. Carefully check the monitoring plots and discuss anything that looks strange with the analysis shift crew.
- Fill out the Shift check list once every shift
HMS | SHMS | TARGET | RADIATOR | I (uA) | RASTER | DURATION | Q (C) | TRIGGER | DAQ | STATUS | |||||
P | THETA | P | THETA | ||||||||||||
#1 (MODE 10) | 4.95 | 19.1 | (+) | 4.835 | 17 | (-) | LH2 | out | 70 | 2x2 | 0:05 | production | COIN | done | |
#1 (no radiator) | 4.95 | 19.1 | (+) | 4.835 | 17 | (-) | LH2 | out | 70 | 2x2 | 1:00 | 0.25 | production | COIN | 50% |
#1 (MODE 10) | 4.95 | 19.1 | (+) | 4.835 | 17 | (-) | LH2 | in | 70 | 2x2 | 0:05 | production | COIN | done | |
#1-0 | 4.95 | 19.1 | (+) | 4.835 | 17 | (-) | LH2 | in | 70 | 2x2 | 5:30 | 1.39 | production | COIN | done |
#1-0 (Dummy) | 4.95 | 19.1 | (+) | 4.835 | 17 | (-) | Dummy | in | 40 | 2x2 | 2:00 | 0.29 | production | COIN | done |
#1-1 | 4.95 | 19.1 | (+) | 4.835 | 17 | (-) | LH2 | in | 70 | 2x2 | 12:00 | 3.02 | production | COIN | 0.95C |
#1-1 (Dummy) | 4.95 | 19.1 | (+) | 4.835 | 17 | (-) | Dummy | in | 40 | 2x2 | 3:20 | 0.48 | production | COIN | defer |
TIME (days) | 1.00 | ||||||||||||||
Charge(mC) | 5,430 |
Phase 2: Mid-E/low-t
Additional instructions:
- Trigger:
- ps6=0 is production trigger
- alse enable ps1 and ps4, pre-scaled to <100Hz
- Remember to click "save" when changing the pre-scalers!
- MODE 10 runs:
- Set DAQ to MODE 10 and click "save" in the pre-scaler GUI
- Remember to go back to MODE 9 when done (and click "save" again!)
- J/psi-007 Instructions for Shift Takers
- Do a 50k replay for every run. Carefully check the monitoring plots and discuss anything that looks strange with the analysis shift crew.
- Fill out the Shift check list once every shift
HMS | SHMS | TARGET | RADIATOR | I (uA) | RASTER | DURATION | Q (C) | TRIGGER | DAQ | STATUS | |||||
P | THETA | P | THETA | ||||||||||||
#2 (MODE 10) | 4.6 | 19.9 | (+) | 4.3 | 20.1 | (-) | LH2 | in | 70 | 2x2 | 0:05 | production | COIN | done | |
#2 | 4.6 | 19.9 | (+) | 4.3 | 20.1 | (-) | LH2 | in | 70 | 2x2 | 36:00 | 9.07 | production | COIN | 27.5% |
#2 (Dummy) | 4.6 | 19.9 | (+) | 4.3 | 20.1 | (-) | Dummy | in | 40 | 2x2 | 12:00 | 1.73 | production | COIN | DEFER |
TIME (days) | 2.00 | ||||||||||||||
Charge(mC) | 10,800 |
Phase 3: high-t point
CHANGE HMS HGC PRESSURE TO 0.35atm
Additional instructions:
- Trigger:
- ps6=0 is production trigger
- alse enable ps1 and ps4, pre-scaled to <100Hz
- Remember to click "save" when changing the pre-scalers!
- MODE 10 runs:
- Set DAQ to MODE 10 and click "save" in the pre-scaler GUI
- Remember to go back to MODE 9 when done (and click "save" again!)
- J/psi-007 Instructions for Shift Takers
- Do a 50k replay for every run. Carefully check the monitoring plots and discuss anything that looks strange with the analysis shift crew.
- Fill out the Shift check list once every shift
HMS | SHMS | TARGET | RADIATOR | I (uA) | RASTER | DURATION | Q (C) | TRIGGER | DAQ | STATUS | |||||
P | THETA | P | THETA | ||||||||||||
#3 (MODE 10) | 4.08 | 16.4 | (+) | 3.5 | 30 | (-) | LH2 | in | 70 | 2x2 | 0:05 | production | COIN | done | |
#3 | 4.08 | 16.4 | (+) | 3.5 | 30 | (-) | LH2 | in | 70 | 2x2 | 192:00 | 48.38 | production | COIN | 22.4% |
TIME (days) | 8.00 | ||||||||||||||
Charge(mC) | 48,384 |