RC meeting and Run Plan, Friday 29th March

From HallCWiki
Revision as of 13:46, 29 March 2019 by Sjdkay (talk | contribs) (Created page with "= RC Meeting Information = <b> RC Daily Meetings are at 3:30 PM, 2nd floor Counting House Meeting Room </b> * Bluejeans remote connection information: To join the Meeting:...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigationJump to search

RC Meeting Information

RC Daily Meetings are at 3:30 PM, 2nd floor Counting House Meeting Room

  • Bluejeans remote connection information:
 To join the Meeting:
 https://bluejeans.com/861439920
 To join via Room System:
 Video Conferencing System: bjn.vc -or-199.48.152.152
 Meeting ID : 861439920
 To join via phone :
 1)  Dial:
   +1.408.740.7256 (US (San Jose))
   +1.888.240.2560 (US Toll Free))
   +1.408.317.9253 (US (Primary, San Jose))
   (see all numbers - http://bluejeans.com/numbers)
 2)  Enter Conference ID : 861439920

Useful Links

Current Status

Current Run Plan

  • We are currently running the dummy target for our first kinematic point at this beam energy, Q2 = 4.4, W = 2.74, low epsilon centre setting
  • Once the dummy target is done (~ 1 hour) we will switch back to LH2 and run until tomorrow day shift (Unless the accelerator fairies are VERY kind to us tonight and we get incredible beam/stats through swing)
  • After this, we switch to the left setting (SHMS moves to 13 degrees) for this kinematic point
  • We'll then run at this point until approximately day shift on Sunday, after this it's onto the next kinematic point (where we'll be for quite a while!)
  • This next setting has a very low SHMS angle (the lowest we can move to remotely), I will give an update on the timing of this as things become clearer over the weekend
  • Whichever shift this ends up on will have to monitor the rotation very vigilantly as it is in progress

Notices in Effect for Shift Crew

  • Please take a screenshot of the spectrometer angles when they are moved to a new position and make a log entry. If working on a kinematic that lasts several days take an image daily.
  • Pay attention to the notices posted in the counting house regarding HMS Q1/Q2.
  • If HMS interlocks when ramping, check the live camera image of the HMS power supplies for smoke/water before clearing the interlock.

Special Requests

  • Alexandre had a short access earlier today during the downtime, he has requested another one early next week during the beam studies/RF recovery down periods.