PolHe3 Target Coil Rotation Plan, Mar 2020

From HallCWiki
Revision as of 09:28, 3 March 2020 by Brads (talk | contribs) (Created page with "== '''Target coil rotation planned for March 13--20''' == * Nominal 1-week downtime in Hall C to rotate target coils, install new cell, and transition to d2n program <!-- Hidd...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigationJump to search

Target coil rotation planned for March 13--20

  • Nominal 1-week downtime in Hall C to rotate target coils, install new cell, and transition to d2n program
  • Status update on oven plate and other cell mounting hardware (Arun?)
  • Kepco power supply status (Bill/Todd?)
  • Status Update for target cell Austin (Xiaochao?)
    • Wall and window thicknesses done
    • Only 'Reduced set' of density measurements available now, will continue measurements this week (issues with laser at UVa?)
    • It would be best for it to arrive at JLab on March 10 (at the latest) to allow locals to mount cell in oven plate before they get involved with target work in Hall.
  • Lots of preplanning to be completed (RadCon, Techs, S&A, Target group, etc)
    • Had job walkthrough meeting this (Monday) morning with the above parties -- so far, so good
    • Must coordinate Tech support with the parasitic test installation plans
  • RW-II training for JP, Arun, Brad (Complete the training documentation and take the RW-II test if you haven't already done so)