June 25, 2022
From HallCWiki
Current Status
- Accelerator status:
- Can't deliver more than 20 uA, probably stuck here till Monday
- Experiment status:
- pionLT continues to make progress on run plan, though we are still behind schedule, unless Ops is able to deliver 80 uA at >50% efficiency
- On page 33 of run plan. New Setting: Q2=2.45, W=3.20, x=0.21, high ε data taking. 12,000 of 30,000 pions completed at this setting.
- LD2-> Dummy -> LH2 -> SHMS Angle change
Current Run Plan
Notices in Effect for Shift Crew
- Please pro-rate ABU for max current limit in run plan (uA) in beam time accounting. For example, if we receive 15 uA instead of the max_current_limit in the run plan, then the ABU should be: ABU_prorated = 15/(max current limit) * ABU
- Check the HMS/SHMS rates for when production starts, since for Heep coin. production SHMS saw higher rates. Make sure shift crew takes snapshot of scalers at every setting
- When analyzing LD2 or Al dummy or LH2, please leave the target_mass_amu in the standard.kinematics as that of the proton, but when analyzing the data with the pionLT script, specify the target used, as different targets will have different ranges in the cuts when integrating the missing mass peak. Refer to log entry: https://logbooks.jlab.org/entry/4005387 These instructions are given in the pionLT run plan.
- Keep on eye on HMS DC chamber wire maps. See current issues
Current Issues
- shift crew continues to see HMS DC noise outbursts more frequently, see log-entries:
- See log-entries: https://logbooks.jlab.org/entry/4005325 , https://logbooks.jlab.org/entry/4005330
- study noise dependence on HMS DC thresholds, and found that noise temporarily went away @ DC threshold 5.8 V, but re-appeared on the next runs see log-entry --> https://logbooks.jlab.org/entry/4005624 This issue will have to be addressed today during maintenance day
- Hall C BCMs and Accelerator BCMc (i.e., MPS BCMs) mismatch --> https://logbooks.jlab.org/entry/4005801
- I would think this is just a scale factor missing between the two measurements? Usually S. Wood did this in the past. I have notified S. Wood in the log-entry
- Gains and offset need to be update https://logbooks.jlab.org/entry/4006872
Planned Accesses to the Hall
- Need new plan to address HMS DC noise. Replace cards with spares? Check thresholds on cards and LV.
Planned Accelerator Configuration Changes
- Possibly take down machine Monday to get us to higher currents
Special Requests
- Install telegram on RC Phone (DONE)