Q^2 Scan of Azz

With 24 PAC days + commissioning time, we can make a Q^2 scan of Azz from 0.8 (GeV/c)^2 < Q^2 < 2.0 (GeV/c)^2. The two higher points (1.2 and 2.0) seem to be the most interesting, but also take the most time (7 and 14 days, respectively). With an extra 3 days, we can also take points at Q^2=0.8, 0.6, and 0.3 (GeV/c)^2.

Q^2=2.0 (GeV/c)^2, E_{beam}=11.0 GeV, PAC Time = 336 hours
2014-04-04-q2-200.png
Q^2=1.2 (GeV/c)^2, E_{beam}=8.8 GeV, PAC Time = 168 hours
2014-04-04-q2-120.png
Q^2=0.8 (GeV/c)^2, E_{beam}=6.6 GeV, PAC Time = 36 hours
2014-04-04-q2-080.png
Q^2=0.6 (GeV/c)^2, E_{beam}=4.4 GeV, PAC Time = 12 hours
2014-04-04-q2-055.png
Q^2=0.3 (GeV/c)^2, E_{beam}=2.2 GeV, PAC Time = 6 hours
2014-04-04-q2-030.png