Run Plan for Kaon LT 10.6GeV End Game
From HallCWiki
Strategy
- Finish remaining 3 kinematic points
- Minimize risk:
- Finish full 6deg. dataset first to avoid rotation issues
- Next get partial dataset for last kinematic points
- Ensure we have Al Dummy for each setting by front-loading them at each kinematic change
- Aim to finish by Saturday, leaving buffer for contingencies or opportunistic revisiting of other kinematic points
Run Plan Schematic
Owl | Day | Swing | ||||
Wednesday | 6deg. LH2 | 6deg. LH2 | 9deg. Dummy | 9deg. LH2 | ||
Thursday | 9deg. LH2 | 12deg. Dummy | 12deg. LH2 | 12deg. LH2 | ||
Friday | 9deg. LH2 | 9deg. LH2 | 9deg. LH2 | |||
Saturday | 12deg. LH2 | 12deg. LH2 | 12deg. LH2 | buffer | ||
Sunday | buffer | buffer | buffer | |||
Monday | buffer | X | X |