Run Plan for Kaon LT 10.6GeV End Game
From HallCWiki
Strategy
- Finish remaining kinematic points
- Minimize risk:
- Finish full 6deg. dataset first to avoid rotation issues
- Next get partial dataset for last kinematic points
- Ensure we have Al Dummy for each setting by front-loading them at each kinematic change
- Aim to finish by Saturday, leaving buffer for contingencies or opportunistic revisiting of other kinematic points
Run Plan Schematic
Owl | Day | Swing | ||||
Wednesday | 6deg. LH2 | 6deg. LH2 | 9deg. Dummy | 9deg. LH2 | ||
Thursday | 9deg. LH2 | 12deg. Dummy | 12deg. LH2 | 12deg. LH2 | ||
Friday | 9deg. LH2 | 9deg. LH2 | 9deg. LH2 | |||
Saturday | 12deg. LH2 | 12deg. LH2 | 12deg. LH2 | buffer | ||
Sunday | buffer | buffer | buffer | |||
Monday | buffer | X | X |
Detailed Run Plan
Wednesday Owl
- Same setting as previous shift (Q2=5.5, W=3.02, x=0.4)
- Same target as previous shift (LH2)
- Desired beam current: 45µA
- Do NOT run at higher beam current (will kill tracking efficiency)
- Adjust PS1 (SHMS-3-4) to give pre-scaled rates close to 100Hz (should be same as previous shift)
- Adjust PS3 (HMS ELREAL) to give pre-scaled rates close to 100Hz (should be same as previous shift)
- Ensure PS0 = 0 (This is the physics trigger!) (should be same as previous shift)
- Make a log entry if changing pre-scalers!
- Try to take 1 hour runs
Wednesday Day
- Same setting as previous shift (Q2=5.5, W=3.02, x=0.4)
- Same target as previous shift (LH2)
- Desired beam current: 45µA
- Do NOT run at higher beam current (will kill tracking efficiency)
- Adjust PS1 (SHMS-3-4) to give pre-scaled rates close to 100Hz (should be same as previous shift)
- Adjust PS3 (HMS ELREAL) to give pre-scaled rates close to 100Hz (should be same as previous shift)
- Ensure PS0 = 0 (This is the physics trigger!) (should be same as previous shift)
- Make a log entry if changing pre-scalers!
- Try to take 1 hour runs
- Instructions for the last hour:
- If beam really bad in last hour: prepare next kinematic setting/target for swing (see below)
- If beam still good in last hour: continue taking data until swing