Hall C Weekly Meeting - April 1, 2013
From HallCWiki
Jump to navigationJump to search- Andy Kenyon
- Doing Cryowork this week
- Moving small green blocks from hall (to send to Hall D) and replacing with large green blocks
- Leak detector being used from HMS checkout is flakey
- Dave Gaskell
- Asked when the Moller SC magnet will be replumbed. Depending on workload, will do this before July HMS cooldown.
- Joe Beaufait
- G0 cable move continuing. Mounts for patch panels have been set in wall
- Got a UPS for Hamlet/Aerogel
- Paul Brindza
- Design Projects:
- Compton upgrade and Moller coils
- Noble gas Cerenkov
- Mod to lead glass stand for SHMS
- SHMS dipole exit flange/spool
- Assembly of SHMS Shield House Sliding door
- ELIC concept layout
- 12 GEV- SHMS:
- SHMS Bogies delivered to Hall C last week
- Spool/bearing and bearing housing moved to Hall C from ESB
- Bids in for SHMS Structure assembly- eval underway- decision this week
- Q1 Yoke stacking about half way done, contract with Stainless Metalcraft for Vessels
- DC Power Supplies 3,4 &5 for Dipole, Q2 and Q3 tested and in shipping ETA Mid May
- HB Helium vessel parts machining, design of LN2 shield and Vacuum vessel, HB yoke complete
- Dipole Q2 & Q3 yoke steel machining about 80 % done
- SHMS Dipole prototype coil winding
- SHMS Dipole, conductor testing, all 6 pieces tested so far are acceptable for use, E layer and F layer, G layer still at JLAB
- SHMS Dipole Full Design Review April 23/24
- Design Projects:
- Stephen Wood
- Next Hall C User meeting will be in August. Users and staff can express date preferences at the doodle poll.