Hall C Weekly Meeting - April 29, 2013
From HallCWiki
Jump to navigationJump to search- Walter Kellner
- Working on cleaning up radiation/contamination area near the dump. Plan to remove a piece of the remaining Qweak pipe.
- Filling in pot holes in the hall
- Leak detector repairs
- The C-can, which now will not be used, has been used to ESB for storage.
- Mike Fowler - SOTR
- The company awarded the SHMS assembly contract, Ward Marine Enterprises, has posted their bond and received a notice to proceed.
- A pre-construction meeting will be held this week
- This company is new to the lab, so the workers will need training.
- Estimated start time, mid may
- Mike Fowler - Engineering notes
- Bert is working on the SHMS slit/collimator design
- Paulo is working on the Compton upgrade
- Dan is working on the beam dump shield (shields SHMS detectors from dump at small angles)
- Gary and Steve Furches are working on the SHMS vacuum system
- Steve Lassiter, Eric, and Paul are preparing for the Lehman review.
- Howard Fenker
- Paul Brindza, Howard Fenker, and Kathleen Jones (procurement) made a visit to SigmaPhi. Contract negotiations are still in progress
- Yoke stacking for Q1 is 85% done
- Manufacturer for the vessel contracted
- MSU received thick metal plates for the HB and will start building the aluminum vessel.
- Joe Beaufait
- Support for beamline magnet power supplies (Compton and Moller) turned over to DC power group
- The G0 signal cables have been cut back for the new patch panel location
- HV cables are being rolled up.