Hall C Weekly Meeting - August 12, 2013

From HallCWiki
Jump to navigationJump to search
  • Walter Kellner
    • Jerry finished engraving work for Steve Lassiter (12GeV)
    • Jessica is fine tuning HMS LVDT calibration with Lassiter
    • Installation of SHMS drive motor is in progress
    • Leak checking individual stinger lines on Anaconda transfer line
    • Assisting Regina group with SHMS Heavy Gas Cerenkov detector in ESB.
  • Joe Beaufait
    • Finished cleanup from replacement of rack power strips (replaced because of flood)
    • Gave walkthrough training
    • Clean power is back on in Hall
  • Paul Brindza
    • 12 GeV
      • Prototype full size dipole coil wind started July 29, 20 turns prior to August recess.
      • Prototype coil wind complete by Sept 13 and VPI by Sept 27
      • Production Dipole coil winding start Sep 30th
      • Second winding line at SigmaPhi delivery Set 15/commission Sept 30
      • Quad (2&3) Final Design Review will be Oct 1-3
      • Horizontal Bend cryostat Helium vessel about 50 % welded
      • Q1 cold mass assembly proceeding, cryostat Fab proceeding and will be done before cold mass
      • Ward Marine making excellent progress welding the SHMS carriage- nominal finish Aug 21
      • Shield House awarded to Hylton Construction- start Sept 2nd
      • HMS cool down delayed until October- DC supply tests ~ November or later
      • SHMS controls electronics “half rack “ added on top to keep “five rack footprint” in shield house
    • Design Projects
      • SHMS sieve slit
      • SHMS vacuum
      • SHMS lead glass shield and access platform
      • Moller upgrade
      • Moller quad coil best and final underway
  • Other
    • Brad Sawatzky - a pump down test of the heave gas cerenkov is in progress
    • Narbe Kalantarians reports that Hampton is finishing the last wire chamber plane