Hall C Weekly Meeting - August 26, 2013
From HallCWiki
Jump to navigationJump to search- Andy Kenyon
- Packing up current leads for shipping
- Jessia and Boogie working on HMS valve controls
- Preparing a shipping frame to send LAD detectors to ODU
- Mike Fowler
- The contractor is working to finish up the SHMS steel work
- Welding should finish this week or early next
- Bogies to be installed next week
- Machine shop making shim plates for the bogies
- The contractor that will pour the concrete for the shield house is working on their safety plan.
- The concrete pouring work is expected to take 4 months
- Joe Beaufait
- Has bids back on the SHMS main power panel and feed breaker
- Counting house can be accessed, but phones are not on
- G0 cable cabinets are in place. Will finish cable rerouting in September.
- Working on SHMS flex conduits/trays