Hall C Weekly Meeting - December 3, 2012
From HallCWiki
Jump to navigationJump to search- From Andy Kenyon (some relayed by Joe)
- SOS doors are off and removed from hall
- Getting ready to start cutting SOS shield house (may be as early next week, depends on contractor schedule)
- Cleaning up floor from demolition of concrete pad - may be complete this week.
- Pressure washing truck ramp.
- From Joe Beaufait
- Blew nitrogen through one of the worst cables that run under hall floor. TDR indicated 60 feet of water in cable - after blowing nitrogen for 2 days, it looks great.
- Let sit over the weekend to see if water would seep back in - still looks good.
- Rest of the ~100 cables should be easily recoverable. Nitrogen dewar on order.
- Counting House work has started. Electrical conduit in 2nd floor ceiling will cause complications. Estimated full completion of project by mid-May.
- From Mike Fowler
- Bert is working on UVa SHMS cerenkov. Some recent design changes.
- Paulo is finishing up Moller coils. Starting on Compton.
- Dan working on stands for cryogenics.
- Steve F. working on spectrometer vacuum. This will transition to Gary.
- Gary has been working on shield house.
- Steve L. working on superconducting cable issues.
- Eric working on magnet FEA.