Hall C Weekly Meeting - December 3, 2012

From HallCWiki
Jump to navigationJump to search
  • From Andy Kenyon (some relayed by Joe)
    • SOS doors are off and removed from hall
    • Getting ready to start cutting SOS shield house (may be as early next week, depends on contractor schedule)
    • Cleaning up floor from demolition of concrete pad - may be complete this week.
    • Pressure washing truck ramp.
  • From Joe Beaufait
    • Blew nitrogen through one of the worst cables that run under hall floor. TDR indicated 60 feet of water in cable - after blowing nitrogen for 2 days, it looks great.
    • Let sit over the weekend to see if water would seep back in - still looks good.
    • Rest of the ~100 cables should be easily recoverable. Nitrogen dewar on order.
    • Counting House work has started. Electrical conduit in 2nd floor ceiling will cause complications. Estimated full completion of project by mid-May.
  • From Mike Fowler
    • Bert is working on UVa SHMS cerenkov. Some recent design changes.
    • Paulo is finishing up Moller coils. Starting on Compton.
    • Dan working on stands for cryogenics.
    • Steve F. working on spectrometer vacuum. This will transition to Gary.
    • Gary has been working on shield house.
    • Steve L. working on superconducting cable issues.
    • Eric working on magnet FEA.