Minutes Hall C Meeting 2/25/2013

  • Walter Kellner
    • The floor of the SOS shield house was cut up and removed.
    • The SOS bogies were removed
    • The SOS pivot was removed. The SOS base frame is supported on posts.
    • Lockwood Brothers is on site and preparing for the SOS base frame removal
    • The Hall C crane is down for repairs. A crane is being rented to support the base frame removal
    • Working on getting the C-can (G0 cryo supply) removed this week.
  • Mike Fowler
    • The SHMS rail installation is near completion
    • Cleanup and painting of the rails and rail bases in progress
    • The contract for SHMS structure assembly will be awarded soon
  • Joe Beaufait
    • Hoffman ductwork on the HMS has been done to the junction box
    • The G0 water cooled power leads were located for use with the Moller or SHMS power supply tests. They may be recoated with rubber.
    • Halfway done disconnecting cables at the G0 patch panel (Panel needs to be moved for SHMS clearance)
    • Continuing to air flush flood damaged HMS cables
    • Continues to offer Hall C walkthrough training. 4 people trained last week
  • Paul Brindza
    • Noble Gas Cerenkov and Vacuum pipe design
    • Moller quad coil design continues
    • Modelling work on SHMS Dipole coil design
    • SHMS cryo equipment arriving
    • Surveyors going to Craft to fiducialize magnet yokes
    • SMI (Oxford) has started stacking yoke steel
    • Sigma Phi is redesigning tooling to support vacuum impregnation of coils
  • Bert Manzlak
    • Reminder to keep training up to date and remove skills not needed from EJTA