Hall C Weekly Meeting - February 4, 2013
From HallCWiki
Jump to navigationJump to searchMinutes Hall C Meeting 2/4/2013
- Steve Smith: -
- A brief safety culture discussion.
- Showed 2 slides – Safety Trend Analysis.
- Safety culture survey results were presented.
- Andy Kenyon:
- Cutting continues on SOS Hut. Back wall and floor remain. “G0” gas lines mostly down, but not all. C cans removal awaits crane in hall.
- Joe: Electrical
- Nitrogen tank is empty and needs to be refilled.
- Polyflow chamber gas lines appear structurally sound.
- Will replace interdict sieving only.
- Starting to assembly new Hoffman duct routing together so SHM can clear.
- Start soon G0 patch panel removal.
- Roll of ribbon cable sent to Hampton.
- Old G0/Qweak cables are still too hot to send off site.
- Mike Fowler:
- SHMS rail plates in place on rods.
- Need tighten bolts, place and align rails and grout.
- Expect completion in of this month.
- SHMS structure assembly contract still in bidding stage with a planned start date in March.
- Andy Kenyon:
- Lockwood starting SOS steel support structure cutting in March
- Paul Brindza:
- Design work on Noble gas Cherenkov detectors underway.
- Design work on SHMS vacuum exit spool piece proceeding, but is tricky.
- New Moller Quad coils will be wound using new copper which has yet to be ordered.
- SHMS door opening hardware being designed so as to function similarly to existing HMS door.
- Accepted alignment report form Craft for SHMS double boggie wheel assemblies.
- Last 3 Danfisik power supplies at factory waiting final manufacture tests. Should be here by May 1st. of this year.
- A major break through appears to have occurred in the Sigma-Phi magnet manufacturing schedule. The dipole is now expected end of 2014.
- Q1 and Michigan State quad also expected to arrive by the end of 2014.
- Last SHMS quad delivery expected the middle of 2015.
- Sigma-Phi developed new thermal champing scheme to allow coil winding to proceed. It has not yet been tested in a production setting. Some 20 heat expanded rings must slip onto coil assembly. 2nd coil winding station is now part of manufacturing schedule.
- Formal contract modifications likely only weeks away.
- Greg’s concern about “strange” anaconda routings addressed by Paul.
- It is also possible that the engineers may have simply got their available spigot count wrong.
- Brad:
- 3 VSX crates arrived.
- Flash-ADC test stand being set up.