  • Walter Kellner:
    • SOS roof and front wall have been removed. The side and rear walls remain.
    • G0 gas lines are being removed
    • Most of the SOS rail bed has been removed
    • Cutting up of the SOS base frame (Lockwood) is expected to start mid February.
  • Joe Beaufait:
    • Working on removing HMS cableway demolition
    • Orange conduit for wire chamber gas lines has disintegrated in places. It is suggested that the Polyflow line in these conduits be checked for integrity.
    • Water (ground?) is coming out an electrical panel on the wall of the hall. Power to the panel has been turned off and locked out. Result is no clean power in the tunnel.
    • HMS cables are still being flushed out to remove moisture from the flood.
    • Still doing Hall C walk throughs as needed, generally on Tuesdays. Contact Joe if training is needed.
  • Paul Brindza
    • In Europe visiting Sigma Phi (Q2/Q3/Dipole vendor) and Danfisik (power supply vendor)