  • Andy Kenyon
    • Anaconda work
    • Small work on SHMS electronic parts for Steve Lassiter
    • Test A-can for leaks with new transfer lines
    • Mike Fowler ask for help to move or reduce the radiation material near HMS so that the valves can be operated for HMS cooldown.
  • Mike Fowler - SOTR
    • Pivot in place
    • First piece is bolted up
    • Finished fitting for the first piece to be welded this week.
  • Steve Lassiter - Engineering
    • Work on corrector magnets and shielding for the Compton beamline
    • work on cryo line, detector shield hut and chamber gas lines for SHMS.
    • Eric Sun working on dipole FEA and will be going to Michigan for HB.
    • Steve Lassiter visited the Q1 vendor.
    • Paul Brindza will visit Q2/3 vendor in July.
    • Purge of the HMS has begun and it was surprisingly clean. Cooldown at the end of July.
  • Joe Beaufait
    • Finished HMS cabling on the side of HMS. Just need to be on cover.
    • This week will replace the long power strips in the flooded racks.
    • Go back to working on the G0 cable move.
    • For summer, will be taking Friday off.