Hall C Weekly Meeting - July 2, 2013
From HallCWiki
Jump to navigationJump to search- Andy Kenyon
- Anaconda work
- Small work on SHMS electronic parts for Steve Lassiter
- Test A-can for leaks with new transfer lines
- Mike Fowler ask for help to move or reduce the radiation material near HMS so that the valves can be operated for HMS cooldown.
- Mike Fowler - SOTR
- Pivot in place
- First piece is bolted up
- Finished fitting for the first piece to be welded this week.
- Steve Lassiter - Engineering
- Work on corrector magnets and shielding for the Compton beamline
- work on cryo line, detector shield hut and chamber gas lines for SHMS.
- Eric Sun working on dipole FEA and will be going to Michigan for HB.
- Steve Lassiter visited the Q1 vendor.
- Paul Brindza will visit Q2/3 vendor in July.
- Purge of the HMS has begun and it was surprisingly clean. Cooldown at the end of July.
- Joe Beaufait
- Finished HMS cabling on the side of HMS. Just need to be on cover.
- This week will replace the long power strips in the flooded racks.
- Go back to working on the G0 cable move.
- For summer, will be taking Friday off.