Hall C Weekly Meeting - July 9, 2013
From HallCWiki
Jump to navigationJump to search- Andy Kenyon
- Anaconda work
- Vent A-can and pump down again
- Checked with Radcon about the hot material on the HMS. Radcon would prefer not to move it. Should be fine to contact radcon when needed to access valves.
- Mike Fowler - SOTR
- Welded first two pieces together. Check by contractor welding inspector. Need to be improved.
- After that do continue with next pieces.
- Steve Lassiter - Engineering
- Work on corrector magnets and shielding for the Compton beamline
- work on cryo line, detector shield hut and chamber gas lines for SHMS.
- Eric Sun working on dipole FEA
- Paul Brindza will visit Q2/3 vendor this week.
- Joe Beaufait
- Needed to reorder the clamps for the HMS cable tray cover.
- Work on replacing long power strips in damaged racks.