Hall C Weekly Meeting - March 18, 2013

From HallCWiki
Jump to navigationJump to search
  • Walker Kellner
    • Superconducting wire was moved out of the ESB (to make room for our activities)
    • Some techs are updating their welding certifications
    • Investigated cleaning SC power leads. Having SRF do it is best to meet industrial hygiene requirements.
  • Joe Beaufait
    • G0 cable move in progress
      • Old rack being removed
      • HV cables need to be disconnected
    • HVAC work is going on in the counting house. Roger asks that we check if area under computer floor is sealed from outside while the HV units are out.
  • Steve Lassiter (Engineering)
    • Design:
      • Bert: SHMS sieve slit and snout layouts
      • Paulo: Moller drawings and specification completed, awaiting signatures. Compton beamline working on details for the newer widths.
      • Gary: SHMS Swing Doors drive mechanism details, nearly completed, awaiting comments and checks.
      • Dan: SHMS Barn Door drive mechanism and structure attachment drawings.
      • Steve F: SHMS Shutter hardware assembled. Cherenkov holding tank frame assembly ,ready for checking.
      • Mike: Vendor meetings for SHMS carriage assembly.
    • SHMS:
      • Q1 magnet: Yoke stacking is continuing at SMI. JLAB procured TIG welding wire with Ferrite Number not greater than 5 for sub-contractor.
      • HB magnet : Finished machining of the two side plates completed. QA audit planned for March 27/28 by Eric, Bruce and Howard.
      • SHMS DC Power Supplies: Factor Acceptance Test under way at Danfysik.
      • Dipole: prototype coils fabricated. Samples of pressed VPI conductor held up in customs, FedEx is working on this. ***Auto stamping press has been awarded.
      • Vendor meeting for SHMS support structure today.