Hall C Weekly Meeting - March 24, 2014
From HallCWiki
Jump to navigationJump to search- Paul Brindza
- HB magnet
- Shimming superconducting internal bus
- Welding Helium vessel
- Q1
- cold mass in LHE vessel
- Fiducializing LHE vessel to transfer Mag centerline outwards
- Welding LHE vessel
- Closed up in about a week.
- Dipole
- Production coil winding on wind station #1
- 1st layer complete
- second layer started last week ~ 25 % done
- Intermediate end spacer bolt hole did not line up, due back Wed.
- Finish second layer next week ( April 4th)
- VPI (Vacuum Impregnation) week April 7 - 11
- Production wind station # 2 start after successful VPI
- All dipole conductor required (6 pieces) completely consolidated
- Dipole LHE and OVC vessels on order from Chastigny
- LN2 shield on order form Barriquand
- ASME weld design by APAVE
- Quads 2/3
- Quad winding tooling on order, production hold until first VPI successful
- HB magnet