Hall C Weekly Meeting - March 24, 2014

From HallCWiki
Jump to navigationJump to search
  • Paul Brindza
    • HB magnet
      • Shimming superconducting internal bus
      • Welding Helium vessel
    • Q1
      • cold mass in LHE vessel
      • Fiducializing LHE vessel to transfer Mag centerline outwards
      • Welding LHE vessel
      • Closed up in about a week.
    • Dipole
      • Production coil winding on wind station #1
      • 1st layer complete
      • second layer started last week ~ 25 % done
      • Intermediate end spacer bolt hole did not line up, due back Wed.
      • Finish second layer next week ( April 4th)
      • VPI (Vacuum Impregnation) week April 7 - 11
      • Production wind station # 2 start after successful VPI
      • All dipole conductor required (6 pieces) completely consolidated
      • Dipole LHE and OVC vessels on order from Chastigny
      • LN2 shield on order form Barriquand
      • ASME weld design by APAVE
    • Quads 2/3
      • Quad winding tooling on order, production hold until first VPI successful