Hall C Weekly Meeting - March 25, 2013

From HallCWiki
Jump to navigationJump to search
  • Walter Kellner
    • SHMS parts are being moved from the ESB to the hall
    • Work on C-can ongoing
    • Moping up water from leaks (near labyrinth/beam entrance)
  • Mike Fowler (SOTR and for Engineering Group)
    • Structure installation pre-bid meeting was held Monday, 18 March. 7 contractors attended.
    • SHMS Bogie delivery and Dipole Yoke steel pickup scheduled for Wednesday, 27 March.
    • Ongoing Design work:
      • Bert - SHMS Vacuum system, Sieves and GEM detector.
      • Dan - SHMS Cryo system & Barn Door
      • Gary - SHMS Swing door.
      • Paulo - Compton.
      • Steve F. - Calorimeter installation drawings.
      • Lassiter - SHMS Q1 contract & Hall B conductor soldering.
      • Eric - SHMS Dipole & Bender contracts, SHMS Cryo.
  • Joe Beaufait
    • Counting room under construction.
      • New lights installed
      • Old HVAC is gone and building extension for new unit in place
      • Finish work to be done, but wall and floor penetrations are covered to keep out rain.
    • No Hall C isolation transformers found yet (for Hamlet/Aerogel)
    • G0 Patch panel move under way.