Hall C Weekly Meeting - March 25, 2013
From HallCWiki
Jump to navigationJump to search- Walter Kellner
- SHMS parts are being moved from the ESB to the hall
- Work on C-can ongoing
- Moping up water from leaks (near labyrinth/beam entrance)
- Mike Fowler (SOTR and for Engineering Group)
- Structure installation pre-bid meeting was held Monday, 18 March. 7 contractors attended.
- SHMS Bogie delivery and Dipole Yoke steel pickup scheduled for Wednesday, 27 March.
- Ongoing Design work:
- Bert - SHMS Vacuum system, Sieves and GEM detector.
- Dan - SHMS Cryo system & Barn Door
- Gary - SHMS Swing door.
- Paulo - Compton.
- Steve F. - Calorimeter installation drawings.
- Lassiter - SHMS Q1 contract & Hall B conductor soldering.
- Eric - SHMS Dipole & Bender contracts, SHMS Cryo.
- Joe Beaufait
- Counting room under construction.
- New lights installed
- Old HVAC is gone and building extension for new unit in place
- Finish work to be done, but wall and floor penetrations are covered to keep out rain.
- No Hall C isolation transformers found yet (for Hamlet/Aerogel)
- G0 Patch panel move under way.
- Counting room under construction.