Hall C Weekly Meeting - May 20, 2013
From HallCWiki
Jump to navigationJump to search- Walter Kellner
- Using 40ft I-beam with wheels to hold Anaconda and be able to work on it and move it around the hall.
- Chillers checked out. Clean up at dump continues.
- Lead sheets for 12 GeV shipped out
- Making shipping containers for shipping HB and Q1 cooling leads
- Mike Fowler - SOTR
- Still working on Safety plans for the SHMS structure work.
- Lift plans have been approved
- Mike Fowler - Engineering notes
- Bert/Steve work on the SHMS vacuum system
- Paulo is working on the Compton upgrade
- Dan is working on the beam dump shield (shields SHMS detectors from dump at small angles)
- Gary fire safety and warm gas lines
- Mike on refitting the Anaconda.
- Joe Beaufait
- Set work order for electricians to install upper cable tray for G0 reroute work.
- Cable reroute in HMS junction box is being worked on.
- Walk throughs for the contractors.