Hall C Weekly Meeting - November 12, 2012

From HallCWiki
Jump to navigationJump to search
  • From Kelly Mahoney
    • Presentation concerning Personnel Safety Systems Integrity (slides)
    • Have been several recent incidents of PSS systems being negatively impacted by (planned) work around the lab, including Hall C.
    • Please keep PSS systems in mind as you plan your work.
      • Walk the area
      • Follow cables and conduits to make sure they are not PSS related
      • Check electrical panels for PSS and RadCon circuit breakers
      • Use work planning tools (ATLis, HCList, etc.) ( After meeting Andy Kenyon added PSS people to HCList)
  • From Andy Kenyon
    • More SOS removal work
    • This week working on getting back off of SOS
    • Lifting plates attached to SOS doors
  • From Joe Beuafait
    • Discussed repair of PSS equipment damaged by the Great Flood with Kelly last week. ODH system verified in January 2013. Work on "submerged racks" will start Early 2014.
    • Beamline receptacles will be off tomorrow for electrical work (more flood aftermath).
    • Hoffman duct work may require help from Hall C techs, electricians short on manpower (lost term employees).
    • SHMS liquid cooled leads are in - need to find appropriate storage.
    • Need to put in Facilities request for replacement of power strips on racks (again).
  • From Brad Sawatzky
    • 2-factor authentication on its way for Counting House computers
    • Will be limited to computers actually running CODA or other slow controls
    • No apparent change if you are sitting in CH (mostly)
    • Talk to Brad for more details
  • From Narbe Kalantarians
    • Closed up one half-chamber of SHMS drift chambers and adding electronics.
    • Flowing nitrogen through it now - might apply voltage soon.
    • One more plane has been strung.
    • All the planes are in hand and are plan to start stacking another chamber.
  • From Howard Fenker
    • 12 GeV Project completion deadline has been extended to December 2016. Note that this is the deadline for overall project completion - not planned completion date.
    • Hall C "ready for beam" still planned for Spring 2015.
    • Q1 delivery estimate holding steady for last couple months at Feb. 2014.
    • FRIB taking over management of bender construction. Overall, should be good news for the project. Delivery estimate May 2014.