Hall C Weekly Meeting - November 4, 2013

From HallCWiki
Jump to navigationJump to search
  • Andy Kenyon
    • Finished welding the Anaconda. Leak checking and LN2 heat leak checking in progress.
    • Developing an OSP so that the SHMS Utubes and transfer line can be tested. A test with 5ATM helium is planned.
  • Mike Fowler
    • The wall of the shield house next to the beamline was poured.
    • Pouring boron loaded concrete will be done next
    • A pre-bid meeting was held today for vendors interested in doing the installation of the SHMS utility deck
  • Joe Beaufait
    • 100 more cables were loaded into the cable tray (G0 Cable move)
    • The counting room console has not been painted yet
    • The SHMS power supplies that are not being stored in the hall could survive flooding up to 20". When installed, the supplies will be on the SHMS deck
  • Mike Fowler for Engineering
    • Paulo is working on the Compton polarimeter. Drawings have been passed to an engineer for review
    • Bert Metzger is working on installation drawings for the lead walls in the shield huts
    • Dan is working on LAD support design
    • Steve Furches: target design work for Silviu
    • Gary is assisting with SOTR work for the concrete contract
    • Eric is preparing for the dipole finite element analysis review
    • Steve Lassiter is working on controls, and the Q1 and HB contracts
  • Michael Moore
    • Preliminary results from the fringe field analysis confirm that without mitigation, the fringe fields will bend the beam too much for SHMS angles up to 10 degrees.
  • Jay Benesch
    • Discussed the schedule for startup of the accelerator. The OPS schedule shows cryo finishing on November 19 and 5 MeV beam starting on November 16.