Hall C Weekly Meeting - October 7, 2013

From HallCWiki
Jump to navigationJump to search
  • Walter
  • Mike Fowler
    • SHMS Shield House concrete forming is progressing well
    • Contractor is working towards pouring the walls to half height this Friday
  • Joe Beaufait
    • Reviewed and approved the Hall D solenoid power supply SOP and helped work out out a clean power grinding issue.
    • Reviewed the new Consolidated Hall Walk Through Procedure
    • Developing the Hall C walk through map, but waiting for a hall map from the designers so that he can input the relevant items into the presentation.
    • New accelerator electricians have been informed of the upcoming electrical work
    • Counting house power is on and the lock that was put on by a Harris employee has been transferred to Jlab.
    • The control room laminate is on and the painting of the control panel is still awaiting completion
    • Has a scheduled walk thru with Henry Robertson on Tuesday to go over the changes in the PSS system and movement of the cabling on the south wall
  • Steve Lassiter
    • Gary is working on SOTR for the concrete pouring of the SHMS Shield hut and laying out the remaining cryogenic plumbing
    • Paulo is working with the Moller and Compton, upstream Beamline
    • Bert is working with SHMS Angle Scales, Q1 FEA Model jobs, SHMS Magnet bellows, beam line and Sieve
    • Dan is working on detail drawings for the SHMS shield wall
    • Mike is working on the SHMS installation, concrete pouring of the SHMS Detector walls
    • Eric is working on HB contract and FEA for the SHMS dipole
    • Steve is work on the Q1 contract, HMS cryogenoc valve work, RRR measurements for the SHMS Conductor, Tosca models
    • Paul is working on the SHMS Cosine theta Quads FDR meeting at Sigma Phi in France. SHMS Dipole conductor oversight at Sigma Phi.