Hall C Weekly Meeting - September 16, 2013
From HallCWiki
Jump to navigationJump to search- Andy Kenyon
- Work is continuing on the Anaconda. Making up new sections of the outer flexline.
- Will load containers with plastic that will be used in the special SHMS concrete this week.
- Supported Joe's cable pulls
- Mike Fowler
- The contract to assemble steel base frame of the SHMS is complete and the SHMS is self supported by the pivot and bogies.
- The forms for concrete pouring are being fabricated in the hall. The form defining the inner wall of the electronics hut is done.
- Rebar for the concrete will arrive soon.
- A test batch of concrete was done last week.
- Joe Beaufait
- Have sent emails or made phone calls to all known parties with pipes or cabling in the keep out zone on the hall south wall.
- Made tray fill calculations and weight calculations for the SHMS flexible pivot. Am scheduled to meet with Gary Vattelana tomorrow to go over the design.
- The old SOS DC cable run can be used to provide the AC cable run to the pivot. We will have to remove the old cabling and bridge a short conduit from the clean power box.
- The GE Spectra panel enclosure has arrived and can be mounted as soon as the platform is in place. The buses and breakers are due to be shipped in the next two weeks.
- Electrical worker training has been updated in preparation for the safety inspection that is to start next week.
- Paul Brindza
- Reported on the status of the winding of the prototype coil for the SHMS Dipole. File:Prototype SHMS Dipole Coil September 16, 2013.pdf
- Bert Manzlak
- An "Electrical Safety including Lock Tag & Try" assessment will be conducted September 24-26, 2013. The assessment plan can be found at: [1].
- The JLab EH&S Notable Event
report describing the incident in which a student was shocked while testing a HV cable is available.
- Brad Sawatzky
- JLab now has an account at github.com where public and private git repositories can be hosted. Contact Brad for more information.