Hall C Weekly Meeting - September 23, 2013

From HallCWiki
Jump to navigationJump to search
  • Mike Fowler
    • The contractor doing the concrete shield house is receiving rebar today.
    • They are planning to pour the shield house floor on Friday
    • Mike will be out the rest of the week. Gar Vetelana will be SOTR, assisted by Bert Metzger.
  • Joe Beaufait
    • Working with Paul Powers to get electric contractors to restore power to the counting house
    • Met with Gary V and agreed on basic design parameters for the SHMS pivot flexible tray.
    • Requested a quote for a flexible tray to use at the pivot. Qweak tray is too small.
    • Parts for the Spectra Panel AC power panel are tricking in.
    • Contacted Telecom to restore phones in the counting house
  • Walter Kellner
    • Andy and Bert are picking up the SHMS shielding panels (lead?)
    • Boogie and Matt are working on the Anaconda
    • There is some more work coming up in Blue Crab to disassemble the clean room.
    • Discussed if SHMS power supplies can be moved into hall.
  • Stephen Wood