Hall C Weekly Meeting - September 23, 2013
From HallCWiki
Jump to navigationJump to search- Mike Fowler
- The contractor doing the concrete shield house is receiving rebar today.
- They are planning to pour the shield house floor on Friday
- Mike will be out the rest of the week. Gar Vetelana will be SOTR, assisted by Bert Metzger.
- Joe Beaufait
- Working with Paul Powers to get electric contractors to restore power to the counting house
- Met with Gary V and agreed on basic design parameters for the SHMS pivot flexible tray.
- Requested a quote for a flexible tray to use at the pivot. Qweak tray is too small.
- Parts for the Spectra Panel AC power panel are tricking in.
- Contacted Telecom to restore phones in the counting house
- Walter Kellner
- Andy and Bert are picking up the SHMS shielding panels (lead?)
- Boogie and Matt are working on the Anaconda
- There is some more work coming up in Blue Crab to disassemble the clean room.
- Discussed if SHMS power supplies can be moved into hall.
- Stephen Wood
- Attended the IT steering committee meeting. File:IT Steering Committee Sept 2013.pdf, File:IT Steering Committee Sept 2013 notes.pdf