Hall C Weekly Meeting - September 30, 2013
From HallCWiki
Jump to navigationJump to search- Walter
- Working on the anaconda. The pieces of the outer tube have been welded together and leak checked. Superinsulation is being placed on the inner tube.
- Preparing for shipment of a LAD plane to ODU this week.
- Thursday Blue Crab clean room dissassembly may be postponed until next Monday.
- Joe Beaufait
- Spectrum panel parts, extra breakers, front panel, etc. are here and stored in the Mezzanine
- Facilities is installing new laminate on the counting house control panel and desk surfaces.
- One the PR is approved the painting console to be completed by the weekend in grey color
- Steve Lassiter
- Eric Sun is working on the dipole finite element analysis
- Paulo is working on the Compton drawings
- Moller coils have been awarded
- Dan is working on the decking and shielding behind the SHMS
- A platform is being designed to access the SHMS shower counter. The SHMS will need to be moved to a specific angle in order to access the detectors from the platform.
- Gary & Bert are taking over ast construction SOTR while Mike while is out.
- The concrete floor of the SHMS counting house has been poured. The plywood forms for the walls are being placed.
- Steve is analyzing field changes made to the SHMS Q1.
- Steve Wood
- Presented slides discussing work planning and controls aspects of recent events and accidents. Slides include physics division guidance on work planning. File:Work Plannning And Controls.pdf
- Larry Cardman forwarded information about the American Institute of Physics seeking applicants for their State Department Fellowship