RC Meeting, Wednesday, October 21 , 2021
From HallCWiki
Jump to navigationJump to search
RC Meeting Information
RC Daily Meetings are at 10 am, remote connection link: https://bluejeans.com/861439920
Accelerator Status
- Accelerator went down after LCW issue in the SAB last night. Water conductivity remained too high to restore beam until this morning. Photos: https://logbooks.jlab.org/entry/3928348
- Accelerator maintenance day underway
- Work in tunnel until mid-afternoon
- Lock up machine, RF recovery (several hours)
- Beam restoration
- Beam to halls by midnight (if all goes well)
- Another pass change on Friday (Hall A to 4 pass) -> maybe this will change?
Hall C Status
- So far we have collected about 3868 pions (as of 7:30 am) in this configuration
- Hall C is in Controlled Access
Current Run Plan
- Upon beam restoration, execute the abbreviated beam restoration procedure outlined here: https://logbooks.jlab.org/entry/3928364
- Continue data taking until early Nov
Current Issues
- Replace flow switches for (HMS?) magnet power supplies: next opportunistic access (Joe Beaufait) ( PENDING )
- HB LHe has been stable since Saturday owl -> some valve adjustments on Monday
- Target ladder camera was identified to be bad: Joe Beaufait will order camera ( PENDING )
- Still running with no UPS on the SHMS cryo controls - Steve L. will put in PR for batteries and UPS. ( PENDING )
- HCCAM02 not functioning (lift required to replace).