Difference between revisions of "RC Meeting, Tuesday, November 9, 2021"
From HallCWiki
(→Special Requests) |
(→Special Requests) |
||
Line 31: | Line 31: | ||
Hall Work tomorrow: | Hall Work tomorrow: | ||
# aerogel change (Vladimir) | # aerogel change (Vladimir) | ||
− | # target training (Greg) | + | # target training (Greg, in CH) |
# general work (Heidi) | # general work (Heidi) | ||
# change to 5-pass (accelerator) | # change to 5-pass (accelerator) |
Revision as of 09:58, 9 November 2021
Contents
RC Meeting Information
RC Daily Meetings are at 10 am, remote connection link: https://bluejeans.com/861439920 There is a 10:00 RC meeting today, 11/03/2021!
Accelerator Status
- Running beam to C and D (not sharing slit until after pass change)
Hall C Status
- Taking elastic singles
- Last night downtime caused by:
- Al dummy operational limit exceeded https://logbooks.jlab.org/entry/3938967
- Loss of connection to cdaq, but Brad was able to resolve: https://logbooks.jlab.org/entry/3939223
- Loss of communication with SHMS dipole, Ellen made access early this morning
Current Run Plan
3-pass physics run plan:
- elastic singles
- (polarity change)
- Heep coin 2 setting (run 13062) dummy run
- delta scan: begin with SHMS part first
Current Issues
- Replace flow switches for (HMS?) magnet power supplies: next opportunistic access (Joe Beaufait) ( PENDING )
- HMS Q3 insulating vacuum spikes generating annoyance alarms that take minutes to recover. https://logbooks.jlab.org/entry/3930175 Noise levels on transducers look OK, but Junaid's plot indicates Q3 is burping: https://logbooks.jlab.org/entry/3932992 .
- Serious HB LHe low liquid level alarms. https://logbooks.jlab.org/entry/3933051 Always seems to start with a subtle, simultaneous increase in level in Q1/2/3. https://logbooks.jlab.org/entry/3929152 .
- Target ladder camera was identified to be bad: Joe Beaufait will order camera ( PENDING )
- Still running with no UPS on the SHMS cryo controls - Heidi replaced, but need to check charge https://logbooks.jlab.org/entry/3937512
- HCCAM02 not functioning (lift required to replace-Brad is tracking this replacement).
Special Requests
Hall Work tomorrow:
- aerogel change (Vladimir)
- target training (Greg, in CH)
- general work (Heidi)
- change to 5-pass (accelerator)
Useful Links
- How the harp scans and carbon hole target should look (see links):
- carbon hole target beam centering procedure:
- Resetting the "ioc heartbeat epics communications" (start by clicking on the heart at upper left of the magnet controls screen
- Fall 2021 Shift Schedule
- Hall-C Live Status
- Hall-C Logbook
- MCC White Board