Jump to navigationJump to search- Status
- Kaon LT status page.
- Accelerator is working to understand the increase in beam trips at higher currents.
- Plans - Physics by Friday 7 am
- Finish the "center" kinematics (by sometime in the first half of swing); then move to the "right" kinematics (SHMS small angle, 7.74 deg) and take 43% of min goal of 51 K
- Ask for beam energy measurement: ~ 2h
- Go for lumi scans (both low and high rates): ~8 h
- Plans - Access Friday
- Will re-confirm with RadCon for Friday 7am survey
- SHMS aerogel tray change: ~6-8 hours
- Howard will go in to check on the over-active group of wires in HMS DC1X2
- 3HC07A harp checkout