*''Status''
 
*''Status''
 +
** Took elastic data until midnight. Nearly finished. Just 1/2 of last point.
 +
** Midnight accelerator took the beam away to do injector work Beam basically off since then.
 +
 +
*''Analysis''
 +
** HMS optics . https://hallcweb.jlab.org/DocDB/0009/000991/001/HMS%20Optics.pdf
  
  
 
*''Issues''
 
*''Issues''
 +
** Still manual change JT3 value. As become fairly stable.
 +
** RF work on Tuesday. Work on JT3 then.

Revision as of 15:21, 30 September 2018

  • Status
    • Took elastic data until midnight. Nearly finished. Just 1/2 of last point.
    • Midnight accelerator took the beam away to do injector work Beam basically off since then.


  • Issues
    • Still manual change JT3 value. As become fairly stable.
    • RF work on Tuesday. Work on JT3 then.