- Down for System Recovery (~4hrs) today, should be up and running again this afternoon
- In the midst of Kin Group 16 (three points only)
Time-Ordered Run Plan
- (Beam Returns)
- Kin16.6 (finish up Dummy and LH2)
Kin16.7 (NOTE: NOT 16.7A!!!)- Kin16.7A
SHMS POLARITY CHANGE
Kin15.7 (NOTE: NOT 15.7A!!!)- Kin15.7A
- Kin15.6
- Kin15.4A
Reminders
- Take one HMS monitoring run each shift
- For all settings, for each target, split the desired charge between three runs
- Listed currents are estimates. For runs at less than 60uA, increase current until SHMS singles rates are between 400k-500k.
Issues
- Owl Shift workers needed this week (Shift Signup)
Planned access to the hall
- Mark: escorted access to reset crate during RF Recovery