Run plan/To do list - December 1 2017

From HallCWiki
Jump to navigationJump to search

To do list in preparation for running

  • General
    • Locking up tonight, even though beam is not imminent - need to checkout arc dipole power supply.
    • If Hall B is able to take beam this weekend, CW beam in Hall C unlikely. Hopefully will at least get tune beam to the dump.
    • Need to execute Jay Benech's SHMS beam steering test plan before we can start commissioning.
    • target cool down ongoing (complete?)
    • Condense hydrogen in target on Monday
  • Beamline
    • Small quad tripped off on overtemp last night
  • DAQ and Trigger
    • Single arm 3/4 trigger ready - PID trigger setup underway
  • SHMS - general
    • Shutter work complete (?)
    • Shielding work complete


  • HMS - general
    • Issues with HMS quads


  • SHMS - detectors
    • Ready - DC2 shield removed?


  • HMS - detectors