Run plan/To do list - December 1 2017
From HallCWiki
Jump to navigationJump to searchTo do list in preparation for running
- General
- Locking up tonight, even though beam is not imminent - need to checkout arc dipole power supply.
- If Hall B is able to take beam this weekend, CW beam in Hall C unlikely. Hopefully will at least get tune beam to the dump.
- Need to execute Jay Benech's SHMS beam steering test plan before we can start commissioning.
- target cool down ongoing (complete?)
- Condense hydrogen in target on Monday
- Beamline
- Small quad tripped off on overtemp last night
- DAQ and Trigger
- Single arm 3/4 trigger ready - PID trigger setup underway
- SHMS - general
- Shutter work complete (?)
- Shielding work complete
- HMS - general
- Issues with HMS quads
- SHMS - detectors
- Ready - DC2 shield removed?
- HMS - detectors