Run plan/To do list - March 2 2017
From HallCWiki
Jump to navigationJump to searchTo do list in preparation for running
- General
- Hall lockup scheduled for Friday 3pm
- Beam steer up to the hall on Monday day with SHMS magnets OFF (procedures from Jay are posted under daily run plan for Monday March 6)
- Target cool down and SHMS magnets ON on Tuesday during beam studies - Dave M. and Mike confirmed that controlled access is enough
- HMS magnets should be ON before Monday 8 am - need update from Jack
- Issues with the he flow at the beam dump - Dave G. is following that story need update
- SHMS - general
- Remove plexiglass protection cover for SHMS HG - DONE
- HMS - general
- Remove plexiglass protection cover for HMS DC - DONE
- Mag locks on the HMS hut door not wired right now - Joe/Chuck will work on it today IN PROGRESS
- Andy tells me that the status lights for the HMS shutter are not working - Chuck is fixing it IN PROGRESS
- HMS hut wall back in place to complete the hut - DONE
- HMS aerogel out - DONE
- HMS moved to 15 deg - DONE
- Target
- Target chamber alignment: DONE
- The alignment will be re-check after the HMS is put at 15 deg - survey was happening at 2:43 pm; need update
- Andy connected the downstream beam line back to the chamber and Dave M. started Hall C scattering chamber vacuum pumps
- Dave Meekins goes in on Tuesday during day shift (beam studies) to cold? He in one of the loops; he needs controlled access only
- SHMS - detectors
- Brad started flowing argon in the NGC - high flow rate; he will switch to low flow rate tomorrow -> more than 99% pure Argon
- HMS - detectors
- The aerogel slider thingy is sticking out right now in the HMS hut (has not been pushed back in after the detector removal yesterday); Chuck will take care of that
- Other
- training session tomorrow at 2 pm in the Hall C counting house for all shift takers
- target training session tomorrow at 1:30 pm with Greg for few