Run plan/To do list - November 30 2017
From HallCWiki
Jump to navigationJump to searchTo do list in preparation for running
- General
- Issue with Hall C arc-string power supply discovered during hot checkout - testing with dummy-load today and tonight
- NO lockup for hot checkout tonight
- Target training right now
- Shift "show and tell" at 1 pm Friday - featuring Brad S. and Mike F.
- Hall lockup at 5:30 pm tonight for hot checkout
- Hall lockup scheduled for Friday 4pm
- target cool down (helium) Friday
- Condense hydrogen in target on Monday
- Beam over the weekend looking less likely - all shifts until Sunday DAY shift are "on call" (don't come unless notified)
- Beamline
- Fast raster ready (FSD issue resolved)
- One BCM cavity on blue platform can't be tuned (ok - we have 2 more on that platform + BCM1/BCM2)
- DAQ and Trigger
- Emphasis on coincidence trigger/analysis for now
- Single arm 3/4 trigger ready - still some work to do on PID trigger (ELREAL, ELCLEAN, etc.)
- SHMS - general
- Shutter work nearing completion
- Shielding work in hut ongoing
- HMS - general
- HMS rotated to ~70 degrees last night, 13.5 degrees today
- SHMS - detectors
- HMS - detectors