Next: Troubleshooting
Up: Hall C User Howto
Previous: Enge controller and monitor
Splitter is controlled by MCC. Call MCC when we need to change the setup
of Splitter. When we need the ramping in case of power down etc.., call MCC
and ask for them to do as follows,
- Set the current to 900A(Max.).
- Stay for 4 minutes.
- Set the current to 0A(Max.).
- Stay for 4 minutes.
- Set the current to 900A(Max.).
- Stay for 4 minutes.
- Set the nominal current 844(?)A (Check the small paper on the display).
Stephen A. Wood
2005-06-17