User name M.M
Log entry time 11:01:49 on January 9,2008
Entry number 148501
Followups:
keyword=FPP Hit rate problems
Please make an entry when you power cycle a crate. Run# 67876 is pretty bad for chamber A&B and still for C&D. I assume that a power cycling of ROC 13 has been performed since the run lasted "only" 30min. Nevertheless for run 67881 problems in chamb C&D are still remaining. Everything went back to normal after run#67890.
FIGURE 1