User name cdaq

Log entry time 08:11:18 on January 19, 2008

Entry number 148953

keyword=Beam Time Accounting
Hall C

01/19/08 0000-0800
Experiment #: E04-108/E04-019
Shift Leader: A. Puckett
Shift Workers: P. Carter, H. Baghdasaryan

00000100020003000400050006000700Total Time
Acceptable Beam
in Use
0.970.260.000.000.240.000.000.211.69
Beam Available
but Not in Use
0.000.710.991.000.520.970.990.525.70
Beam Not Available
or Unacceptable
0.020.030.010.000.230.030.010.270.60
Accelerator Con-
figuration Change
0.000.000.000.000.000.000.000.000.00
Experiment
Ready
1.000.290.010.000.480.000.000.482.26
Planned Config-
uration Change
0.000.000.000.000.000.000.000.000.00
Unplanned
Experiment Down
0.000.701.001.000.521.001.000.525.73
Hall not
ready reasons
Target0.000.000.000.000.000.001.000.521.52
DAQ0.000.000.000.000.000.000.000.000.00
BigCal0.000.000.000.000.000.000.000.000.00
FPP0.000.000.000.000.000.000.000.000.00
HMS0.000.701.001.000.521.000.000.004.22

Comments: HMS dipole problems for most of shift, then target problems toward end of shift

Data Entry by: A. Puckett