Log entry time 18:46:32 on December 16, 2011
Entry number 244732
keyword=Daily summary and plan through weekend
Owl:
- Shift summary https://hallcweb.jlab.org/hclog/1112_archive/111216075434.html
- Beam limited to < 50 uA due to Left Dump Ion Chamber FSD (LDIC-FSD), so at 01:00 it was masked, full beam delivered, unmasked and worked fine ever since.
- Beam ugly and causing HIGH alarms: W plug differential, W plug water supply, GEM enclosure ion chamber, target upstream ion chamber
- 2 Coulombs of crummy beam with IHWP in
Day:
Swing: Goal = LH2 Production, IHWP = out , need 6.5 hours
- Shift summary
- Good beam established ~ 18:00
- 180 uA on LH2
- W plug scan
- Resume LH2 Production running
Coming Owl: LH2 Production, IHWP = in, need 8 hours
Saturday Day and Swing:
- N à Delta for ~ 1 hour
- Resume LH2 Production
- IHWP = in if needed to complete previous set of 8 hours
- IHWP = out if previous set of 8 hours completed
- Afternoon: Measure helicity magnet slopes
- Resume LH2 Production, alternating IHWP in/out every 8 hours of beam.
Sunday:
- Owl = LH2 Production
- Day = Moller measurements then LH2 production
- Swing = LH2 Production
Monday:
- Owl = LH2 Production
- Day = Energy Measurement, then Drive position differences with helicity state
- Swing = LH2 Production
Figure 1 Close out plan
2011 Close Out Plan-v2.pdf