August 8, 2022

From HallCWiki
Jump to: navigation, search

RC Meeting Information

RC Daily Meetings are at 11:00 (am) via Zoom and in person in the counting house meeting room (2nd floor)

  • Zoom remote connection information:
 Join ZoomGov Meeting
 https://jlab-org.zoomgov.com/j/1607100885?pwd=ZFBsRTFsYm5Zb0laZ0tyZXNjcEE0QT09
 Meeting ID: 160 710 0885
 Passcode: 595071
 One tap mobile
 +16692545252,,1607100885# US (San Jose)
 +16468287666,,1607100885# US (New York)
 Dial by your location
       +1 669 254 5252 US (San Jose)
       +1 646 828 7666 US (New York)
       +1 669 216 1590 US (San Jose)
       +1 551 285 1373 US
       833 568 8864 US Toll-free
 Meeting ID: 160 710 0885
 Find your local number: https://jlab-org.zoomgov.com/u/ab2CekLXgQ

Useful Links

Current Status

  • Completed Q2=3.85, W=2.62, high epsilon (pi-) setting around midnight last night.
  • Started Q2=6, W=2.4 left on OWL shift. Rate was about 1700 pions/hour, suggesting 14-15 hours needed just for this SHMS angle. Followup: ended up with 2462 after diamond cuts.
  • At 7:30, switched to SHMS center setting (Q2=6, W=2.4 pi-). Rate appears to be a little higher, 1857 pions for a 1 hour run (note: 584 pions after diamond cuts). But we are aiming for higher statistics at this setting, so full statistics will take about 16 hours (not including dummy). Followup: if we want 4k after diamond cuts, then we only need 7-8 hours.

Current Run Plan

  • Keep taking data at this setting.
  • Plans for swing and owl to be discussed at RC meeting.
  • 4 pass runplan outline (assuming no downtime):
    • Tuesday morning: pass change
    • Tuesday/Wednesday? ARC energy measurement
    • Tuesday day/swing: Heep coin (9 hours)
    • Tuesday swing/owl: Q2=2.45 (8-9 hours) --> theta_shms <7 degrees
    • Wednesday day: SHMS to 5.5 degrees, continue Q2=2.45
    • Wednesday swing: start Q2=3.85 (32 hours)
    • Thursday day: maintenance day
    • Friday morning: finish Q2=3.85

Notices in Effect for Shift Crew

Current Issues

  • Coffee maker broken! Emergency instant coffee in Counting House.
  • Shifts filled until August 14 - then we have OWL shifts available up to August 19. Lots of openings August 20++.

Planned Accesses to the Hall

  • Maintenance day still scheduled for Thursday, so access may be possible during that time.
  • Aerogel change - still need to finalize day, but it seems likely we won;t be ready for this before the weekend.

Planned Accelerator Configuration Changes

  • Pass change on Tuesday.
  • Pass change (4->3) next week. On nominal beam schedule was to take place Monday (Aug. 15). Told PD that this will likely need to be moved one day.

Special Requests